With an estimated capacity of 360 million liters of sewage treatment per day, the project has completed its initial structural work, and construction is now gaining momentum
Bhushan Gagarani visited the site to inspect the developments firsthand
Brihanmumbai Municipal Corporation (BMC) Commissioner and Administrator Bhushan Gagarani on Saturday visited the ongoing construction of the Bandra Sewage Treatment Plant located near Bandra (West) in Mumbai to review its progress.
ADVERTISEMENT
In an official statement, the BMC said that the plant is being built close to the Bandra Sea Link as part of BMC’s Mumbai Sewage Disposal Project.
With an estimated capacity of 360 million liters of sewage treatment per day, the project has completed its initial structural work, and construction is now gaining momentum. Bhushan Gagarani visited the site to inspect the developments firsthand, it said.
During the civic chief's visit, present at the site were Deputy Municipal Commissioner (Engineering) Shashank Bhore, Chief Engineer of Mumbai Sewage Disposal Project Rajesh Tamhane, Deputy Chief Engineer Rajendra Parab, Project Manager from the contractor L&T Vinaya Hebbar, and Consultant from IVL India Environmental R&D Pvt. Ltd., the civic body stated.
The contract for the construction, operation, and maintenance of the Bandra Sewage Treatment Plant was awarded to Larsen & Toubro Ltd. (L&T) on May 31, 2022 and the construction of it had began on July 5, 2022. The project is expected to be completed by July 4, 2027. The consulting responsibility lies with IVL India Environmental R&D Pvt. Ltd.
During his visit, Bhushan Gagarani reviewed the model of the plant and also viewed its virtual model through Virtual Reality glasses, offering a glimpse of how the completed plant will look. A computer presentation also provided more detailed information about the construction progress, the need for water to support the project, and the newly built 250 KL capacity containerised sewage treatment plant, the statement said.
Shashank Bhore explained that initial construction works have been completed, and now the major construction activities are in full swing. Work will continue through the monsoon seasons of 2025 and 2026 to ensure timely completion. The project’s operational and maintenance period will last for 15 years. Chief Engineer Rajesh Tamhane mentioned that the physical progress of the project has reached 21%, and procurement processes for equipment are also underway. About 265 trees from the project site have been successfully relocated to areas like Malad and Sanjay Gandhi National Park. The workforce involved in the project has completed around 17.7 lakh man-hours to date. Approximately 100 engineers from L&T, 15 consultants from IVL, and 10 engineers from BMC are working daily, with around 800 laborers on-site. Despite large-scale construction, strict safety measures have been followed, with only 10 minor injuries requiring first aid, it said.
Deputy Chief Engineer Rajendra Parab highlighted that while the new plant is being built, the existing sewage plant continues its operations and maintenance. The project is being developed on an 8.36-hectare site, and careful planning has ensured that the work proceeds without any significant challenges. The new plant will include features like sludge treatment, biogas-based electricity generation, a knowledge center, and a viewing gallery. Once completed, the project will improve seawater quality and marine life, benefiting areas like Mahim, Bandra, BKC, Kherwadi, and Santacruz, the BMC said in the statement.
Project Manager Hebbar explained that the current plant processes sewage and discharges it into the sea. In contrast, the new plant will treat 360 million liters of sewage daily in two stages—primary and secondary treatment, with tertiary treatment applied to 180 million liters per day. The plant will use Membrane Bio Reactor (MBR) technology.
After the site visit, Gagarani expressed satisfaction with the progress and instructed the team to accelerate the remaining work. He suggested exploring the possibility of processing the sludge on-site for fertilizer production, reducing transportation costs and time, and improving the overall efficiency of the project. He also recommended engaging with experts in fertilizer production to explore advanced technologies that could be applied within the available space.
