Mumbai: Brace for traffic snarls on Eastern Express Highway

Updated on: 05 April,2025 07:16 AM IST  |  Mumbai
Ranjeet Jadhav | ranjeet.jadhav@mid-day.com

Preliminary work begins on 13.40-km elevated six-lane road connecting Chheda Nagar to Mulund East at Rs 3314 crore; once the work is in full swing, motorists using this stretch may face traffic congestion during morning and evening peak hours and the median will be barricaded

Mumbai: Brace for traffic snarls on Eastern Express Highway

Barricades erected for work related to the elevated road on the Eastern Express Highway on April 4. Pis/Sayyed Sameer Abedi

Listen to this article
Mumbai: Brace for traffic snarls on Eastern Express Highway
x
00:00

Construction of the elevated road from Chheda Nagar in Ghatkopar to Anand Nagar in Mulund East on the Eastern Express Highway (EEH) is set to begin. Once the work is in full swing, motorists using this stretch may face traffic congestion during morning and evening peak hours and the median will be barricaded.


The 13.40-km-long elevated road with three lanes in either direction will be constructed at a cost of Rs 3314.40 crore.


Recently, when this reporter travelled on the stretch between Kanjurmarg East and Mulund octroi naka, the Eastern Express Highway was barricaded at some spots and soil testing work seemed to be in progress. It has been reported that the elevated road will have entry and exit points at Chheda Nagar, Kanjurmarg, Airoli bridge and the Mulund octroi naka.


The contractor who has been awarded the tender for constructing the elevated road will have to complete the work in four years and will be responsible for fixing defects for two years. 

According to an MMRDA official, “Barricades have been placed on the Eastern Express Highway so geotechnical investigation can be carried out. At present, the procedure is taking place between the Airoli flyover and Vikhroli. Subsequently, it will be extended up to Chheda Nagar.”

Asked when the actual work would begin, an MMRDA official said, “Geotechnical Investigation involves boring into the ground to access underground soil data for foundation design. After conducting this procedure, soil strata data will be available. Based on its analysis, the foundation and overall structure design will be prepared and thereafter the actual foundation work shall be started.”

The work started in December 2024 and is expected to be completed by December 2028.

2028
Year project is likely to be completed

Brace for snarls on EEH

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK