21 February,2025 09:22 PM IST | Mumbai | mid-day online correspondent
Representational pic
The Western Railway (WR) will operate a block of three hours on the intervening night of Saturday and Sunday from 1.15am to 4.15am for launching the main girders of Wankhede Foot Overbridge (North) between Churchgate and Marine Lines stations.
The details of the train diversions are given below.
Train cancellations
ALSO READ
Dadar station's platform no. 4 FOB staircase to be closed for repairs
Dadar station's platform no. 4 FOB staircase to be closed for repairs
WR limits platform ticket sales at key Mumbai stations for festive rush
Mumbai: Railway cops on high alert to curb Holi mischief on trains
Western Railway reveals design for eight modern stations on Virar-Dahanu route
Partial cancellations and short terminations
The railways has appealed to passengers to plan their travel based on the diversions.
The Western Railway (WR), while sharing Mumbai local train updates, on Friday said that it will operate a jumbo block of five hours between Santacruz and Goregaon stations on Sunday.
According to an official statement, the Western Railway said that to carry out maintenance work of tracks, signaling and overhead equipment, a jumbo block of five hours will be taken on up and down fast lines between Santacruz and Goregaon stations from 10.00 hrs to 15.00 hrs on Sunday, 23rd February, 2025.
According to a press release issued by Chief Public Relations Officer of Western Railway, Vineet Abhishek, during the block period, all Fast line suburban trains will be operated on Slow line between Goregaon and Santacruz stations.
Some suburban trains will remain cancelled during the block and also some of the Andheri and Borivali trains will be worked up to Goregaon on harbour line.
Block between Vapi and Udvada; Bhilad and Sanjan
Meanwhile, in an another statement, the Western Railway said that a block will be taken on Monday, February 24 between Vapi and Udvada and on Tuesday, February 25 between Bhilad and Sanjan for launching of Composite Girder for construction of Road Over Bridge in lieu of existing level crossings.