Mumbai: BMC completes 36 per cent work on coastal road project

10 July,2021 07:07 PM IST |  Mumbai  |  PTI

The construction of the coastal road project commenced in October 2018 and is worth Rs 12,000 crore

BMC office. File Pic


Mumbai's civic body Brihanmumbai Municipal Corporation (BMC) has informed that 36 per cent work of the coastal road project has been completed so far.

Till now, 90 per cent of filling at the site, 68 per cent of the sea wall and 11 per cent work of the double tunnel has been completed. In a statement issued, the BMC said, "With the slogan 'Happy Journey, Free Breath', 36 per cent of the work of the coastal road of BMC has been completed. 90 per cent of the fill, 68 per cent of the sea wall and 11 per cent of the double tunnel are completed. The work of 'Coastal Road' is going on day and night uninterruptedly!"

The construction of the coastal road project commenced in October 2018. It is worth Rs 12,000 crore. Work was stayed by Bombay High Court in April 2019 on a bunch of petitions against this project but construction was later allowed by Supreme Court in May 2019, vacating High Court's stay after BMC appealed in the apex court.

In 2017, the project was given a green flag by the Maharashtra Coastal Zone Management Authority (MCZMA), Expert Appraisal Committee (EAC) and the Ministry of Environment and Forest (MoEF).

Also Read: Mumbai: Week on, potholes back on Aarey Colony roads

This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!
brihanmumbai municipal corporation mumbai mumbai news bombay high court supreme court
Related Stories